There are the following results for a given period: Expected completion time of the given project = 44 Variance of project completion time = 5

Price:
$14.99
SKU:
118507


Product Description

There are the following results for a given period:

Expected completion time of the given project = 44

Variance of project completion time = 5.54

What is the probability of completing the project over 40 days?

A.   0.957

B.   0.886

C.   0.896

D.   0.853